The SS then said there is a sewer delay again and referred
me to South East Water (SEW) and ask them for further info. I called our land
sales contact and she said no there isn’t a delay and there are 2 families
already living on your street and should I want additional information to contact
the building developer as he can offer more information. After a few more emails to the PD and them forwarding
an email from SEW (without dates on it bit suss) stating there was a sewer
delay until end of April I then spoke with the building developer and he then
advised that a PIC# something SEW gives when the sewer is ready to be connected
and said that it was completed on 9th March! I then told our SS and he said Wow
really well I will call SEW and see what the heck is going on. I thought to myself I can tell you have been
caught out not telling the truth trying to give an excuse for nothing being
done which has created a delay. I also told them we have 2 neighbours living on
our street and one of the homes is 4 doors up and is also built by PD. Hmmmm
PD said their permits department will contact SEW and see
what is going on and will update us with any news.
In addition our new front window hasn’t even been installed
and still sitting in the garage supposedly waiting for the chippy.
Our SS said that the house should be ready in 3 to 3.5
weeks, so fingers crossed as after tiles there is only electrical, plumbing
fitting off and carpet and door knobs.
We met with our tiler and he said they would be done by the
end of this week! And from this point
probably move in 4 weeks’ time! We
really hope so.
Below are pics of the house to date:
Master ensuite about to be tiled
Bathroom tiles
Kitchen from the lounge room- love the glass splash back
Splash back from side view
Rod's walk in robe with window framed
Master bedroom window framed
Random shot of a spare room- just wanted to show the paint colour - "Kid Leather"
Your house is looking really good.
ReplyDelete