Wednesday 18 January 2012

Week 8 and 9

A few things to report for this week...

My DH started his new job!!  :)

Our bricks started being laid on Monday 16th January, ducted heating system in roof cavity, heating ducts in every room and a bathtub frame!

Still haven't seen the rectification work done to the framework but we will be meeting with the SS in the next few days I will follow up with him them as to when that will be completed.

Our temp SS advised the sheet rock will be installed next week and asked if we were wondering why our front door frame wasn't installed.....my DH said yes! SS advised they had received the wrong size and the current one is due sometime this week.



Future Bathtub

Gas point for our future BBQ

Front view of the house

Patio and Master bedroom windows

Sunday 8 January 2012

Week 7

We were advised by our BC that the roughing (plumbing) will be done when the plumbers get back on the 11th of January 2012, but our bricks were delivered on Wednesday (4th Jan).


We went by the site and saw a little bit has been done.  We now have the insulation wrap around the house and yes indeed our bricks have been delivered.


It’s amazing just how much it changes since having the insulation wrap on the house, it really puts a perspective of where ours house and the neighbour’s house sits on out boundary lines.



Our alfresco/patio

Our brick colour - redish brown with a cream streak in the middle

More bricks and windows of bedroom 3 and 4 in the backyard


Our soon to be home is finally taking shape