Thursday 29 December 2011

Week 6

As of now we have windows and a laundry door frame- the front door is there but hasn't been installed yet.

We were told by our building coordinator that the things will starting moving again the week of the 3rd Jan- cant wait to see the bricks!


Master bedroom windows

Lounge room windows

Sliding doors to patio - thankfully we will have 1.8metre fences

Rumpus/Movie room window looking at the backyard

Tuesday 20 December 2011

Week 5

As of yesterday 20th December 2011 we are still waiting on the window frames to be completed and our windows to be installed.  According to our stand-in SS the windows should be installed before Christmas break.

Funny thing....We were across the street taking a front on picture (4th picture below)  noticed a window laying on the grass.  After looking at the lable we noticed it was our ensuite window!!!  We carried it back to our garage and noticed where it was missing from.  I left a message for our stand-in SS today advising him, so it will be interesting if he does something.   Hmmmmm makes you wonder how it got there!

In addition, our home finally has a hat!  That's right we have a roof! 

Our stand-in SS said the bricks should be delivered on 3rd January 2012 and brickies (Aussie term for brick layer) will start in early January.

Our soon to be home is finally taking shape!

 Main bathroon window frame

Looking up in the garage

Friday 9 December 2011

Our Slab and Frame - weeks 3 &4

A lot has change since I last blogged..... we now have a slab and framing!  I can't believe how much has changed in just over 3 weeks. 

We meet our SS on Monday, so hopefully we can build a good relationship with him.

Our slab.....





and our frame!